Dynacor Completes Construction Of New US$ 15-Million Ore Processing Plant

 

MONTREAL, QC - Dynacor Gold Mines Inc. has completed the construction of its new 300-tpd Veta Dorada ore processing plant and has begun the commissioning process. The Veta Dorada plant is located in Chala (southern Peru) in the heart of a major gold producing region of Peru.

The commissioning process will involve the following two steps: Pre-commissioning: Construction of the plant and its sub-units are validated by Veta Dorada's technical team. This also includes testing of the plant's power distribution system, testing the electrical motors and the process control valves as well as the ore conveyor belts, etc.; and Commissioning: A Dry and/or Wet Running. Depending on the process sub-units either dry or wet running is used to test the units individually (crushing, milling, conveyor belts, etc.). The objective being to determine that each sub-unit is functioning correctly.  Operational running. This involves a complete test using mineralized ore, crushing and milling as well as chemical extraction and gold recovery. During this stage all the processes are tested but the yield is not measured.